Project Details



project details with images
Project Id 7 Ref. to Admin Sanction Manoj
Project Name Test Project Manoj Admin Sanction Amount Rs. 100
Address Manoj Ref. To Tech Sanction Manoj
Agency Sreekar agency Tech Sanction Amount Rs. 100
Division Adilabad Division Agreement Number Manoj_123
District Adilabad Agreement Amount Rs. 100
Scheme Agreement Date 01-Dec-2023
User Department DME Completion Date as per Agreement 01-Dec-2023
Current Status Work in Progress Expected Completion Date 31-Dec-23
Stage of Work Plinth Beam Level Cumulative Expenditure Rs. 3,18,32,839
Project Status Remarks REMARKS TEST 03.01.2024 11:55 REMARKS TEST 03.01.2024 13:20 REMARKS TEST 03.01.2024 13:35 REMARKS TEST 03.01.2024 13:45 REMARKS TEST 03.01.2024 11:50 REMARKS TEST 03.01.2024 13:55 Expenditure Current Year
Status Updated On 2024-01-03 13:23:05 Total Target for the Current Year

TSMSIDC